Date Description View
July 2009 Lift core wall from 9 to 10th Storey completed



July 2009 8th Storey completed at Galle Road / Church Side



July 2009 8th Storey completed at Galle Road / LSC side (Sector 2)



July 2009 8th Storey slab completed at Tennis Court / LSC side (Sector 1)



July 2009 8th Storey slab completed at Tennis court / Church side (Sector 1)



July 2009 Concreting to 8th Storey slab in progress (Sector 2)



June 2009 Overall site view from Galle Road Side



June 2009 Overall site view 4 from Church side



June 2009 Overall Site View from Church side



June 2009 Overall site view 3 from Tennis court side



June 2009 Overall site view 2 from LSC side



June 2009 19 Overall site view 1 from LSC side



June 2009 Construction of RC Wall from 7 to 8th Sty in progress



June 2009 Wall formwork from 7 to 8th Sty in progress at Sector 2



June 2009 Fixing of elctrical conduits to 8th sty slab in progress



June 2009 Rebar work to 8th sty slab in progress at Sector 1



June 2009 wall Formwork to 8th slab in progress



June 2009 Formwork to 8th Sty slab in progress at Sector 1



June 2009 Construction of lift core wall from 9 to 10th Sty in progress



June 2009 Construction of RC staircase from 7 to 8th Sty in progress



June 2009 Rebar work to wall from 7 to 8 th sty in progress at Sector 2



June 2009 Construction of RC wall from 7 to 8th Sty in progress at Sector 1



June 2009 jacking up of tower in progress



June 2009 Rebar and formwork to 7th Sty slab in progress at Sector 1



June 2009 Rebar work to lift core wall from 8 to 9th sty in progress



June 2009 Construction of RC wall from 6 to 7th Sty in progress



June 2009 Rebar and formwork to wall from 6 to7 th sty in progress at Sector 1



June 2009 Rebar work wall from 6 to 7th sty in progress at Sector 2



June 2009 Table form to 7th sty slab in progress



June 2009 Rebar work to wall from 6 to 7th sty in progress



May 2009 Overall site view form LSC side



May 2009 Overall site View from Tennis court side



May 2009 Overall site view from Church Side



May 2009 Overall site view from Galle Road Side



May 2009 Rebar work to lift core wall from 8 to 9th Sty in progress



May 2009 Rebar work to wall from 5 to 6Th sty in progress at Sector 2



May 2009 Hacking construction joint to wall at Sector 2



May 2009 Construction of wall from 5 to 6th Sty in progress at Sector 1



May 2009 Installation of M&E services to 5th Sty slab in progress at Sector 2



May 2009 Rebar work to 5th Slab in progress at Sector 2



May 2009 Wall formwork from 5 to 6th Sty in progress at Sector 1



May 2009 Rebar work to 5th sty slab in progress at sector 2



May 2009 External scaffold at Galle Road side



May 2009 wall from 4 to 5th sty in progress at sector 2



May 2009 Rebar work to wall form 5to 6 sty in progress at sector 1



May 2009 Installation of concrete pump’s boom in progress at sector 1



May 2009 Installation of Concrete pump mask in progress at Sector 1



May 2009 Plumbing work to 5th Sty slab in progress



May 2009 Plastering to skin wall in progress at Tennis court side at B1



May 2009 Formwork to 5th sty slab in progress



May 2009 Rebar and formwork to wall from 4 to 5th Sty in progress at Sector 2



May 2009 Rebar work to lift core wall from 7 to 8th sty in progress



May 2009 Formwork to 5th Sty slab in progress at sector 1



May 2009 Rebar and formwork to wall from 4 to 5th sty in progress at Sector 2



May 2009 Rebar work wall from 4 to 5th sty in progress at Sector 2



May 2009 Wall formwork from 4 to 5th sty in progress



May 2009 Rebar work to wall from 4 to 5th sty in progress



April 2009 Overall Site view from LSC side



April 2009 Overall site view from Tennis court side



April 2009 Overall Site View 2 from Church side



April 2009 Overall Site View 1 from Galle Road side



April 2009 Base of external scaffold in progress



April 2009 Rebar work to 4th Storey slab in progress (GL : 20-25 / M-U) in progress



April 2009 Formwork to 4th Storey slab in progress (GL 20-25/M-U)



April 2009 Skim to columns at Basement 2 is in progress



April 2009 Rebar to wall and column (GL : 20/25 / M-Q) in progress



April 2009 Rebar work to wall from 4th to 5th Sty in progress (GL 13-18/B-M)



April 2009 Skim to wall in progress at Basement 1



April 2009 Placing of Table form for 4th sty slab at Church side (GL : 13-18/B-M)



April 2009 Table form placed to 4th Sty slab at LSC side (GL : 13-18/B-M)



April 2009 Rebar work to wall from 3rd to 4th Sty in progress (GL :20-25/M-U)



April 2009 Construction of lift core wall from 5 to 6th Sty in progress



April 2009 Formwork to wall from 3rd to 4th Storey in progress (GL: 11-25/M-U)



April 2009 Jacking up tower crane’s mask in progress



April 2009 Rebar work to 3rd to 4th Storey wall in progress (GL : 23-25/ M-U)



April 2009 Rebar work to wall from 3rd to 4th Storey in progress (GL 13-18/B-M)



April 2009 Rebar work to 3rd storey slab in progress (GL 9-13/M-Q)



April 2009 Formwork to 3rd Storey slab in progress (GL 20-25/M-Q)



April 2009 Rebar work and M&E work in progress to 3rd storey slab (GL : 9-13/M-U)



April 2009 Formwork to 3rd to 4th Storey column in progress (GL 13-18/B-M)



March 2009 Overall Site View 4



March 2009 Overall Site View 3



March 2009 Overall Site View 2



March 2009 Overall Site view 1



March 2009 Installation of external scaffold’s bracket in progress



March 2009 Removing of formwork at L1 in progress



March 2009 Fixing of External Scaffold’s frame bracket in progress



March 2009 Rebar work to lift core from wall 3rd Sty to 4th Sty in progress



March 2009 Table form to 3rd Storey formwork in progress



March 2009 Rebar work to wall from 3rd Sty to 4th Sty (GL : 13-18 / B-M) in progress



March 2009 Flying out table form from 2nd storey to 3rd Sty for 4th sty slab



March 2009 Concreting to 3rd Storey (GL : 13-18/B-M) in progress



March 2009 Rebar work to 3rd Storey slab (GL : 13-18 / B-M) in progress



March 2009 Installation of M&E service to Storey slab (GL : 13-18 / B-M) in progress



March 2009 Formwork to 3rd Storey slab (GL 13-18 / B-M) in progress



March 2009 Removing Formwork at Basement 1 in progress



March 2009 Formwork to 3rd Storey slab (GL : 13-18 / B-M) in progress



March 2009 Placed table form to 3rd Storey slab



March 2009 Skim to columns at Basement 2 is in progress



March 2009 Rebar to wall and column (GL : 20/25 / U-Q) in progress



March 2009 Rebar work to lift core wall from 3rd Sty to 4th Sty in progress



March 2009 Rebar work to W32 wall from 2nd Sty to 3rd Sty in progress



March 2009 Placing Table form for 3rd storey slab (GL : 13-18/B-M) in progress



March 2009 Formwork to W6 wall from 2nd to 3rd sty in progress



March 2009 Formwork to wall from 2nd sty to 3rd sty (GL : 20-25/Q-U) in progress



March 2009 Preparation work to place table form on 3rd sty slab



March 2009 Cast wall from 2nd storey to 3rd storey (GL : 9-18/B-M)



March 2009 Rebar work to wall from 2nd sty to 3rd sty (GL : 9-18-F-B) is in progress



March 2009 Formwork to wall from 2nd sty to 3rd sty (GL : 9-17/G-M) in progress



March 2009 Rebar work from 2nd sty to 3rd sty (GL : 9-18 / F-M) in progress



March 2009 Rebar work to lift core wall from 2nd sty to 3rd sty in progress



March 2009 Rebar work to wall from 2nd storey to 3rd storey in progress



March 2009 Preparation of table formwork in progress



March 2009 Fixing formwork to lift core wall from 2nd storey to 3rd storey in progress



February 2009 Overall site View 5



February 2009 Overall Site View 4



February 2009 Overall Site view 3



February 2009 Overall Site View 2



February 2009 Overall Site View 1



February 2009 Fabrication of table formwork In progress



February 2009 Rebar work to Lift core wall from 2nd to 3rd storey in progress



February 2009 Rebar work to wall from 2nd to 3rd storey in progress



February 2009 Concreting to 2nd storey slab (GL 9-18/B-M) in progress



February 2009 Side formwork to 2nd storey slab in progress



February 2009 Skim coat Basement 2’s column in progress



February 2009 1st layer concreting to 2nd storey (GL 20-25/B-M) in progress



February 2009 Fixing of top layer to 2nd Storey transfer plate (GL 9-18/B-M) in progress



February 2009 1st Storey slab (GL : 20-22/Q-R) in progress



February 2009 Fixing top layer rebar to 2nd storey (GL 9-18/B-M) in progress



February 2009 Preparation work to concrete in progress (GL : 20-22/R-Q)



February 2009 Fabrication of doka formwork in progress



February 2009 Fixing of shear link rebar to 2nd storey transfer plate (GL 20-25/B-M) in progress



February 2009 Fixing of shear link rebar to 2nd storey transfer (GL 20-25/B-M) in progress Fixing of shear link rebar to 2nd storey transfer (GL 20-25/B-M) in progress



February 2009 Fixing of bottom rebar to 2nd storey transfer plate in progress



February 2009 Fixing bottom layer of rebar to 2nd storey transfer plate in progress



February 2009 Formwork to Level 1 slab (GL 2-4/B-C) in progress



February 2009 Rebar work to 2nd storey plate (GL 20-25/B-M) in progress



February 2009 Concreting to 2nd storey transfer plat (GL : B-M/18-25) in progress



January 2009 Overall site view 9 (from LSC side)



January 2009 Overall site view 8 ( from Church side)



January 2009 Overall site view 7 (from Galle road side)



January 2009 Overall site view 6 (from Galle road side)



January 2009 Overall site view 5 (from Tennis court side)



January 2009 Overall site view 4 (from LSC side)



January 2009 Overall site view 3 (from LSC side)



January 2009 Overall site view 2 (from LSC side)



January 2009 Overall Site view 1 (from LSC side)



January 2009 Installation of M&E services at 2nd storey formwork is in progress



January 2009 Brick work to Fuel tank at B2 is in progress



January 2009 Skin coat to column at B2 is in progress



January 2009 Brick work to Pump room at B2 is in progress



January 2009 Fixing shear link rebar at 2nd storey transfer plate is in progress



January 2009 Erection pipe for the side support to 2nd storey transfer plate formwork



January 2009 Side view of 2nd storey transfer plate formwork support



January 2009 Side view of 2nd storey transfer formwork support



January 2009 Rebar work to staircase from L1 to L2 is in progress



January 2009 Continue formwork to 2nd storey (From GL : 23-20/U-Q) transfer plate



January 2009 Installed M&E services pipes at 2nd storey transfer plate



January 2009 Fixing rebar to drop panel to 2nd storey is in progress



January 2009 Continue formwork to 2nd storey transfer plate (from GL : 11/B-M)



January 2009 Erection of pipe to 2nd storey transfer plate formwork is in progress



January 2009 Formwork to 2nd storey transfer plate is in progress



January 2009 Bottom layer of rebar work to 2nd storey transfer plate is in progress



January 2009 2nd storey transfer plate formwork (from GL :13/B-M) is in progress



January 2009 Rebar work to 2nd storey drop panel (GL :M-B/13/18) is in progress



January 2009 Completed bottom formwork to 2nd storey transfer plate



January 2009 Erection of scaffold to 2nd storey transfer plate formwork is in progress



January 2009 Formwork to Wall W1 (2nd layer) from L1 to L2 is in progress



January 2009 Formwork to 2nd (GL B-N/13-19) storey transfer plate is in progress



January 2009 Formwork and rebar work to Staircase from L1 to L2 is in progress



January 2009 Scaffold formwork to 2nd storey transfer plate is in progress



January 2009 Formwork to (lift wall WL2a to WL2d ) from L1 to L2 is in progress Erection of scaffold to 2nd Storey drop panel formwork is in progress



January 2009 Erection of scaffold to 2nd Story Erection of scaffold to 2nd Storey drop panel formwork is in progress Erection of scaffold to 2nd Storey drop panel formwork is in progress Erection of scaffold to 2nd Storey drop panel formwork is in progress



January 2009 Formwork to W1 (1st layer) from L1 to L2 is in progress



January 2009 Rebar work to circular column from L1 to L2 is in progress



January 2009 Formwork to wall W23 from B1 to B2 is in progress



December 2008 Overall Site View 7



December 2008 Overall Site View 6



December 2008 Overall Site View 5



December 2008 Overall Site View 4



December 2008 Overall Site View 3



December 2008 Overall Site View 2



December 2008 Overall Site View 1



December 2008 Scaffold to 2nd Storey slab formwork is in progress



December 2008 Formwork to Lift wall (WL1a to WL1d)from L1 to L2 is in progress



December 2008 Rebar work to W19 from L1 to L2 is in progress



December 2008 Rebar work to circular column from L1 to L2 is in progress



December 2008 Rebar work to circular column from L1 to L2 is in progress



December 2008 Formwork to circular column from L1 to L2



December 2008 Rebar work to lift wall from L1 to L2 is in progress



December 2008 Formwork to Wall from L1 to L2 is in progress



December 2008 Rebar work to Lift wall from L1 to L2 is in progress



December 2008 Formwork to sub station slab is in progress



December 2008 Rebar work to lift wall from L1 to L2 is in progress



December 2008 Rebar work to L1 slab is in progress



December 2008 Rebar work L1 slab is in progress



December 2008 Rebar and formwork to L1 beam is in progress



December 2008 Concreting to L1 slab is in progress



December 2008 Rebar work to column from L1 to L2 is in progress



December 2008 Rebar work to Wall from L1 to L2 is in progress



December 2008 Rebar work to 1st storey beam and slab is in progress



December 2008 Rebar work and formwork L1 beam is in progress



November 2008 Overall site view 4



November 2008 Overall site view 3



November 2008 Overall site view 2



November 2008 Overall site view 1



November 2008 98% of the rubble wall at church side has been completed



November 2008 Surface preparation of the B2 slab soffit is in progress prior to skim coat application



November 2008 Water proofing work of the sump pit at Galle Rd side is in progress



November 2008 Shifting the bar bending yard to 1st sty slab is in progress



November 2008 Formwork of the skin wall from B1 to capping beam is in progress. GL:8-15/P



November 2008 Formwork of the kicker WB4 on 1st sty slab is in progress



November 2008 Rebar work of 1st sty slab beams is in progress.GL:4-15/A’-K



November 2008 Form work of the 1st sty slab is in progress. GL:4-15/A’-K



November 2008 Rebar work of lift core walls on B1 slab is in progress



November 2008 Re prop the B2 slab has been fully completed



November 2008 Re prop the B1 slab is in progress



November 2008 Form work walls WB6a & WB6b on B1 slab is in progress



November 2008 Final inspection be the consultant is in progress for 1st sty slab.Gl : 15-19/B-P



November 2008 Cleaning the 1st sty slab form work is in progress prior to casting.GL:15-19/B-P



November 2008 Rebar work of 1st sty slab beams is in progress GL : 15-19/B-P



November 2008 Rebar work of the 1sty slab beams is in progress GL : 15-19/B-P



November 2008 Form work of 1st sty slab is in progress GL:15-19/B-P



November 2008 Form work & rebar work of the ramp from B1 to 1st has been completed & inspection is in progress prior to casting



November 2008 Formwork of column C11 on B1 slab has been completed for casting



November 2008 Form work of the potable water tank walls on B1 slab is in progress



November 2008 Formwork of the up stand beam B1B28 on genset slab is in progress



November 2008 Rebar work of the up stand beam B1B28 on genset slab is in progress



November 2008 Form work of column C4 on B1 slab is in progress



November 2008 Form work & rebar work of balance portion of the genset slab is in progress



November 2008 Part of the ramp from B1 to 1st sty has been cast



November 2008 Rebar work of the potable water tank walls on B1 slab is in progress



November 2008 Rebar work of column CB20 on genset slab is in progress



November 2008 Formwork of ramp from B1 to 1st sty is in progress at Tennis court side



November 2008 Rebar work of column C4 on B1 slab is in progress



October 2008 Overall site view 4



October 2008 Overall site view 3



October 2008 Overall site view 2



October 2008 Overall site view 1



October 2008 Installation of starter bar is in progress at Tennis court side



October 2008 Rebar work to Beam 1B4 is in progress



October 2008 Formwork to Water tank wall GL : 10-18 is in progress



October 2008 Rebar work to Column from B1 to L1 CB19 is in progress



October 2008 Rubble construction is in progress at church side



October 2008 Formwork to Beam B1B19 is in progress



October 2008 Dismantling of Decking and I-beam is in progress



October 2008 Rebar and formwork to Column From B1 to L1 (GL : 15-19)



October 2008 Formwork to skin wall at church side (GL : 8-15)



October 2008 Formwork to skin wall at GL 15-19 is in progress



October 2008 Formwork to B1 slab GL : 13-15/A-E is in progress



October 2008 Concreting to B1 slab GL : 10-15/P-K is in progress



October 2008 Concreting to B1 slab GL : 10-15/P-K is in progress



October 2008 Formwork to Generator room is in progress



October 2008 Rebar work to B2 slab GL : 8-10 is in progress



October 2008 Formwork to B1 slab GL : 10-15/P-K is in progress



October 2008 Rebar work to skin wall (GL : 15-19) at B1 is in progress



October 2008 Rebar work to skin wall at church side (Gl : 8-15)



October 2008 Formwork to B2 slab GL : E-N/8-10 is in progress



October 2008 Rebar work to B2 slab GL : 8-13/A-E is in progress



October 2008 Rebar work to Skin wall (GL : A-P) is in progress



October 2008 Formwork to Skin wall (GL : 1-8) is in progress



October 2008 Rebar work to B1 slab (GL : 15-19/P-K) is in progress



October 2008 Formwork to Column CB19 from B1 to L1 slab is in progress



October 2008 Formwork to B1 slab (GL : 15-19/P-K) is in progress



October 2008 Dismantling of 1st layer diagonal strut is in progress at Church/ Tennis court side



October 2008 Rebar work to B2 slab (GL : A-E/13-15) is in progress



October 2008 Rebar work to column CB11 is in progress



October 2008 Formwork to wall (WB2) is in progress



October 2008 Rebar work to B2 slab (GL : 8-10/K-P) is in progress



October 2008 Formwork to skin wall (GL : E-N) is in progress at Tennis court side



October 2008 Rebar work to wall (WB@) from B1 to L1 (GL:8/E-K) is in progress



September 2008 Overall site view 5



September 2008 Overall site view 4 at Tennis court / Church side



September 2008 Overall site view 3 at LSC / Tennis court side



September 2008 Overall site view 2 at Galle road / LSC side



September 2008 Overall site view 1 at Church / Galle road side



September 2008 Dismantling of Diagonal strutting has completed at Galle rd / LSC side



September 2008 Installation of tower crane has completed



September 2008 Dismantling of Diagonal strutting in progress at Galle road / Church side



September 2008 Concreting of B2 slab has completed (GL : 10-15/A-E)



September 2008 Rebar work to B1 Sprinkler pump room in progress



September 2008 Inspection of tower installation by Government Authority in progress



September 2008 Load test of tower crane in progress



September 2008 Rebar work to skin wall (GL : K-B) in progress at tennis court side



September 2008 Rebar work to B2 slab (GL : 10-15/B-E) in progress



September 2008 Formwork to lift wall from B3 to B2 in progress



September 2008 Rebar work to Skin wall from B1 to L1 (18-19) is in progress at LSC / Tennis court side



September 2008 Formwork to Skin wall from B1 to L1 (GL: 15-18) is in progress at LSC / Tennis court side



September 2008 Rebar work to Water tank wall from B2 to B1 is in progress



September 2008 Formwork to B2 slab (GL: 13-15/B-K) is in progress



September 2008 Rebar work to lift wall from B3 to B2 is in progress



September 2008 Installation of tower is in progress



September 2008 Concreting to B3 slab (GL: 13-15/B-E) completed



September 2008 Concreting to skin wall from B2 to B1 (GL : 13-19) has completed at Tennis court / Church side



September 2008 Rebar work to B1 slab (GL : K-A/15-19) is in progress at Tennis court side



September 2008 Installation of tower crane is in progress



September 2008 Formwork to B1 slab (GL A-A/4-10) is in progress at Galle road / church side



September 2008 Installation of tower crane is in progress



September 2008 Rebar work to B1 slab (GL : K-A / 15-19) is in progress at Tennis court side



September 2008 B3 slab concrete completed at lift lobby area



September 2008 Rebar work to B3 slab at Lift lobby area



September 2008 Rebar work to Skin wall from B2 to B1 (GL: 13-19) in progress at Tennis court / Church side



September 2008 Formwork to Skin wall from B2 to B1(GL E-A) in progress at Tennis court side



September 2008 Rebar work to B2 to B1 skin wall (GL E-A) in progress at Tennis court side



September 2008 Formwork to B1 slab (GL : K-A / 15-18) is in progress at Tennis court side



September 2008 Dismantling of kingpost is in progress at LSC / Tennis court side



September 2008 Rebar work to B1 slab (GL 4-8/A-P) at Galle road side is in progress



September 2008 Dismantling of diagonal strutting is in progress at LSC / Tennis court



September 2008 Rebar work to B1 slab (GL 4-8/A-P) at Galle road is in progress



September 2008 Rebar work to skin from (GL 1-4) B2 to B1 is in progress



September 2008 Formwork to B1 slab (GL 4-8/A-P) is in progress



September 2008 B1 slab (GL : 15-19/ E-K) at Tennis court / LSC side



September 2008 Rebar work to wall from B1 to L1 (GL 15-18/K-E) is in progress



September 2008 Formwork to B1 slab (GL 4-8/A-P) at Galle Road side



September 2008 Formwork to B1 slab (GL: 15-18/E-K) is in progress at Tennis court side



September 2008 Rebar work to column (GL: 15/N) is in progress at B1



September 2008 Rebar work to B2 water tank slab (GL: A/10-15) is in progress



September 2008 Formwork to B1 slab (GL : 1-2/P-K) is in progress



September 2008 Base of rubble wall is in progress at Church side



September 2008 Formwork to Column drop panel (GL : B/15-18) in progress



September 2008 Rebar work to B1 slab (GL : 15-18/E-K) in progres



August 2008 Overall site view 5 (Church /Tennis court side)



August 2008 Overall site view 4 (LSC/Tennis court side)



August 2008 Overall site view 3 (LSC/Galle road side)



August 2008 Overall site view 2 (Basement 2)



August 2008 Overall site view 1 (Basement 3)



August 2008 Formwork to column drop panel at CB29 &CB20



August 2008 Rebar work to B2 slab in progress at LSC side (GL 4-15/P-N)



August 2008 Formwork to B2 Water tank slab in progress



August 2008 Formwork to B2-B1 skin wall in progress at Galle rd side (GL1-8)



August 2008 Concreting to Water tank room wall in progress



August 2008 Removal of 2nd layer diagonal strutting in progress at Church / Tennis court side



August 2008 Formwork to B1 slab in progress at LSC / Tennis court side (GL N-E-15-19)



August 2008 Concreting B2 to B1 Column WB2 in progress



August 2008 Formwork to Water tank wall at B3 in progress



August 2008 Casted skin wall from B3 to B2 at LSC / Gall rd side. (GL 4-8)



August 2008 Rebar work to B2-B1 column (CB26) in progress



August 2008 Preparation work for B2 slab concreting in progress



August 2008 B3-B2 skin wall in progress at LSC / Tennis court side (4-1)



August 2008 Rebar and formwork to B2 Sprinkler tank slab at church/tennis court side in progress



August 2008 Rebar work to B2 slab (GL 4-10/K-E) in progress



August 2008 Formwork to B2-B1 skin wall at galle rd side in progress (GL P-E)



August 2008 B2-B1 – Rebar work to skin wall in progress at Galle road side (GL E-A)



August 2008 Rebar work to B2 fuel tank slab in progress



August 2008 Installation of M&E service for water tank in progress



August 2008 Rebar work to water tank wall (WB7, WB5B , WB7) in progress



August 2008 B3-B2 Rebar to skin in progress (GL 10-13/A)



August 2008 Removing of B3-B2 formwork in progress (GL 1-4/P-E)



August 2008 Skin wall concrete completed at B3 to B2 (GL:1-4/P)



August 2008 Formwork to B2 slab in progress (GL:8/10) at Church/Galle road side



August 2008 FP-B3, WLB-D1- Rebar and formwork in progress



July 2008 Tower crane’s base and preparation work for beam



July 2008 Rebar work to B2 slab is in progress



July 2008 Concreting to B3 slab is in progress at Church / Tennis court side



July 2008 Rebar work to B2 slab is in progress at Galle Rd / LSC side



July 2008 Rebar work to skin wall in progress at Church / Tennis court side



July 2008 B3 slab rebar work is in progress



July 2008 Excavation work at 30 pile group in progres



July 2008 Installation of waler beam for re-prop is in progress



July 2008 Re-prop of strutting is in progress



July 2008 Formwork to skin at LSC/Tennis court is in progress



July 2008 Installation of Tower crane’s base frame is in progress



July 2008 Basement 3 - Skin wall in progress at church/tennis court side



July 2008 Rebar work to b3 slab in progress



July 2008 Hacking of pile head and hollow-block wall in progress at pilecap PC11H-1



July 2008 Rebar work in progress for pilecap PC30H-1



June 2008 Overall site view 5



June 2008 Overall site view 4



June 2008 Overall site view 3



June 2008 Overall site view 2



June 2008 Overall site view 1



June 2008 Hacking of pile head is in progress



June 2008 Tower crane’s base and preparation work for beam



June 2008 Rebar work to B2 slab is in progress



June 2008 Concreting to B3 slab is in progress at Church / Tennis court side



June 2008 Rebar work to B2 slab is in progress at Galle Rd / LSC side



June 2008 Rebar work to skin wall in progress at Church / Tennis court side



June 2008 B3 slab rebar work is in progress



June 2008 Excavation work to pilecap PC30H-1 in progress



June 2008 Installation of waler beam for re-prop is in progress



June 2008 Re-prop of strutting is in progress



June 2008 Formwork to skin at LSC/Tennis court is in progress



June 2008 Installation of Tower crane’s base frame is in progress



June 2008 Pilecap is in progress



June 2008 Rebar to Tower crane’s base is in progress



June 2008 Rebar to skin wall is in progress at Galle road / Church side



June 2008 Rebar work to Skin wall is in progress at Dennis court / LSC side



June 2008 B2 Slab formwork is in progress



May 2008 Overall site view 5



May 2008 Overall site view 4



May 2008 Overall site view 3



May 2008 Overall site view 2



May 2008 Overall site view 1



May 2008 Formwork to B2 slab is in progress (GL 1-8/A-P)



May 2008 Concreting to sump pit base (GL: 18-19/A-B) in progress at B3



May 2008 Dismantling of 2nd layer diagonal strut in progress at LSC/Tennis court side



May 2008 Leanconcrete has been done at Tennis court side



May 2008 Manual Excavation for lean concrete in progress at Tennis court side



May 2008 Re-bar work to Beam at Basement 3



May 2008 Formwork to B2 slab in progress



May 2008 Rebar work to sump pit in progress at Tennis court side



May 2008 Formwork to skin wall in progress at LSC/Galle road side



May 2008 Dismantling of column formwork in progress at B3



May 2008 Removing of diagonal strut in progress at Galle road / LSC Side at B3



May 2008 Excavation to B3 lift pit area in progress



May 2008 Hacking of pile head to tower crane base in progress Rebar work to column (B3to B2) CB36 in progress



May 2008 Rebar work to column (B3to B2) CB36 in progress Rebar work to column (B3to B2) CB36 in progress



May 2008 B3 to B2 –column CB35, CB 24 & CB 31



April 2008 Overall site view 7



April 2008 Overall site view 6



April 2008 Overall site view 5



April 2008 Overall site view 4



April 2008 Overall site view 3



April 2008 Overall site view 2



April 2008 Overall site view 1



April 2008 Excavation and shoring in progress to B3 lift pit area Removing of 2nd layer diagonal strut in progress at Galle Rd / LSC Side



April 2008 Removing of 2nd layer diagonal strut in progress at Galle Rd Removing of 2nd layer diagonal strut in progress at Galle Rd / LSC SideRemoving of 2nd layer diagonal strut in progress at Galle Rd / LSC Side



April 2008 Concreting to Pilecap PC8H-1 in progress



April 2008 Formwork and rebar to Pilecap PC8H-1 in progress



April 2008 Casting of Pilecap PC2H in progress



April 2008 Rebar work to Pilecap PC8H-1 (GL :15/E) in progress



April 2008 Casted B3 slab (GL: 4) and Pilecap PC12H-1



April 2008 Rebar work to Pilecap PC2H (GL : 18/B) and coloumn in progress



April 2008 Concreting to B3 slab and pilecap PC12H-1



April 2008 Rebar work to Pilecap PC2H (GL : 19/B) in progress



April 2008 Hacking of pile head completed for PC8H-1



April 2008 Preparation work casting at B3 slab and Pilecap PC12H-1



April 2008 Preparation for casting at B3 slab (GL : 1-2/B-N)



March 2008 Overall site view 5



March 2008 Overall site view 4



March 2008 Overall site view 3



March 2008 Overall site view 2



March 2008 Overall site view 1



March 2008 Rebar work to B3 slab (1-5/A-P) in progress



March 2008 Expose of pile for PC4F



March 2008 Rebar work to pilecap PC12H-1 in progress



March 2008 Rebar work to pilecap PC12H-1 in progress Rebar work to pilecap PC12H-1 in progress



March 2008 Casted B3 sump pit



March 2008 Rebar and formwork to B3 sump pit (GL: 1-2/N-P)



March 2008 Cleaning and hacking pile head to PC12H-1 in progress



March 2008 Hacking of pile head to PC12H-1 in progress



March 2008 Rebar work column B3-B2 (CB37 & CB38) in progress



March 2008 Hollow wall to Pilecap PC8H-2 in progress



March 2008 Rebar work to B3 slab sump pit (GL1-2/N-P) in progress



March 2008 Casted B3 slab (GL 8-15/N-P)



March 2008 Installation of 3rd layer waler and diagonal strutting in progress



March 2008 Rebar and formwork to B3 slab (GL: 8-15/N-P) in progress



March 2008 Manual excavation to B3 slab lean concrete (GL:1-4/A-E)



March 2008 Installation formwork to column B3-B2 WB34 & W34



March 2008 Installation of 3rd waler is in progress



March 2008 Installation shoring to 3rd layer waler and soldier pile



March 2008 Hacking of pile head in progress



March 2008 Casting of pilecap PC8H-2 in progress



March 2008 Rebar and formwork to pilecap PC8-H-2 in progress



March 2008 Excavation work to 3rd layer strut in progress



March 2008 Preparation work to B3 slab lean concrete in progress (GL 8-15/N-P)



March 2008 Completed B3 slab (GL 15-19/E-P)



March 2008 Manual Excavation to sump pit (GL 1-2/N-P) in progress



March 2008 Re-bar and Formwork to B3 slab (GL 15-19/E-P) is progress



March 2008 Hacking of pile head and lean concrete completed PC8H-2



March 2008 Re-bar work to Basement 3 slab (GL 15-19/E-P) in progress



February 2008 Reinforcement and formwork to B3 slab (GL B-K/1-3)



February 2008 Lean concrete base of Pilecap PC8-H



February 2008 Installation Soldier pile to 3rd layer strutting works



February 2008 6 pilecap PC4G (CB17)



February 2008 Footing of pilecap PC1D (CB9, CB10 & CB11)



February 2008 CB11 Pilecap



February 2008 Excavation for pilecap is in progress at tennis court / LSC side



February 2008 Excavation to pilecap is in progress at LC/tennis court side



February 2008 Boring work to Soldier pile in progress



January 2008 Overall site view 4



January 2008 Overall site view 3



January 2008 Overall site view 2



January 2008 Overall site view 1



January 2008 Excavation work is in progress to 3rd layer



January 2008 Pilecap BC35 & BC32



January 2008 pilecap BC16



January 2008 Completed pilecap W34 & WB4



January 2008 Installation of soldier pile is in progress



January 2008 Re-bar and formwork to pilecap WB4 is in progress



January 2008 Re-bar work to WB4 is in progress



January 2008 Formwork to pilecap WB4 is in progress



January 2008 Concreting to Pilecap W34 is in progress



January 2008 Formwork to pilecap W34 is in progress



January 2008 Hacking of pile head is in progress



January 2008 Boring work to soldier pile is in progress



January 2008 Lean concrete to base of pilecap WB4



January 2008 Installation of formwork to pilecap W34 is in progress



January 2008 Fabrication of re-bar to pilecap W34 is in progress



January 2008 Installation of Soldier pile is in progress



January 2008 Hacking of pile head to pilecap W34 is in progress



January 2008 Hacking of pile head to pilecap W34 is in progress



January 2008 Exposed pile group for pilecap W34 construction



January 2008 Excavation for pilecap is in progress at tennis court / LSC side



January 2008 Excavation to pilecap is in progress at LC/tennis court side



January 2008 Boring work to Soldier pile in progress



December 2007 Overall site view 5



December 2007 Overall site view 4



December 2007 Overall site view 3



December 2007 Overall site view 2



December 2007 Overall site view 1



December 2007 Installation of 2nd layer king post’s bracing is in progress



December 2007 Completed 2nd layer centre strut



December 2007 Pre-loading is in progress to 2nd layer centre strut



December 2007 2nd layer Diagonal strut is in progress at LSC/Galle Rd side



December 2007 Completed 2nd layer centre strut



December 2007 3rd layer excavation is in progress at Tennis court



December 2007 Installation of 2nd layer waler beam is in progress at LSC side



December 2007 Installation of 2nd layer centre strut is in progress



December 2007 Excavation work 3rd layer strut is in progress at Tennis court side



December 2007 2nd layer waler beam installation is in progress at LSC/Galle rd side



December 2007 Excavation work to 2nd layer strut is in progress at Galle rd side



December 2007 Pre-loading to diagonal strut is in progress at Tennis court / church side



December 2007 Excavation work to 2nd layer centre strut is in progress



December 2007 Welding work to Diagonal strut is in progress at LSC/Tennis court side



December 2007 Installation of Diagonal Strut is in progress at LSC / tennis court side



October 2007 Overall site view 6



October 2007 Overall site view 5



October 2007 Overall site view 4



October 2007 Overall site view 3



October 2007 Overall site view 2



October 2007 Overall site view 1



October 2007 Excavation work to 2nd layer iron works is in progress at hotel side



October 2007 Installation of 1st layer strutting is in progress at Site office side



October 2007 Completed 1st layer diagonal strutting at Galle Road side



October 2007 Excavation work to 2nd layer iron works is in progress at hotel side



October 2007 Installation of 1st layer diagonal brace is in progress



October 2007 Installation of 1st layer center strutting is in progress at church side



October 2007 Concreting to capping beam is in progress at Galle road side



October 2007 Hacking of pile head is in progress



October 2007 Installation 1st layer diagonal strutting is in progress at Galle road side



October 2007 Rebar work to capping beam is in progress at Galle road side (near to site office)



October 2007 Installation of diagonal bracing to King post is in progress (Angsana side)



October 2007 Installation of 1st layer Diagonal strutting beam is in progress at Galle road side



October 2007 Rebar work to capping is in progress at Galle Rd side (near to site office)



October 2007 Formwork is in progress to wall at church side



September 2007 Overall site view 3



September 2007 Overall site view 2



September 2007 Overall Site View 1



September 2007 Triangle strutting is in progress at Carpark side



September 2007 Preparation work to Triangle strutting is in progress (Galle Road side)



September 2007 Excavation work is in progress to 1st layer strutting



September 2007 Hacking of pile head to capping beam is in progress



September 2007 Rebar work to capping beam is in progress at Church side



September 2007 1st layer Waller and strutting at Carpark side



September 2007 Installation of 1st layer Waller is in progress at Angsana side



September 2007 Installation of 1st layer triangle strutting is in progress



September 2007 Installation of bracket to 1st layer Waller is in progress at Angsana side



September 2007 Completed of 1st layer crass bracing of Decking area



September 2007 Installation of Waller is in progress at Angsana complex side



September 2007 Installed 1st layer of Waller at Church Side



September 2007 Installation of Waller is in progress at Angsana complex side



September 2007 PDA test in progress to the working pile



September 2007 PDA test is in progress



September 2007 Hacking of pile head in progress of capping beam (Church side)



August 2007 Site View 6



August 2007 Site View 5



August 2007 Site View 4



August 2007 Site View 3



August 2007 Site View 2



August 2007 Site View 1



August 2007 Installation of Bracket to Waller is in progress (Dennis court side)



August 2007 Excavation work to install Waller (Dennis court side)



August 2007 Hacking work to capping beam is in progress (Galle road side)



August 2007 Hacking CBP to capping beam is in progress (Church side)



August 2007 Excavation work is in progress (Church side)



August 2007 Installation of decking panel is in progress



August 2007 Excavation work in progress to capping beam



August 2007 Concreted capping beam at Church side



August 2007 Excavation work to capping is in progress (church side)



August 2007 Installation of decking panel is in progress



August 2007 Shoring work to capping beam is in progress



August 2007 Installation of metal decking panel is in progress



August 2007 Installation Secondary beam to decking panel is in progress



August 2007 Installation I-beam to Decking panel is in progress



August 2007 Concreting to capping is in progress (Church side)



August 2007 Excavation work to install I beam for decking panel in progress



August 2007 Fixing formwork is in progress to Capping beam (Church side)



August 2007 PDA test in progress



August 2007 Concreted capping beam at Church side



August 2007 Installation of Kingpost in progress



August 2007 Fixing of formwork to Capping beam in progress (Tennis court side )



August 2007 Hacking work is in progress for capping beam (Galle Rd side)



July 2007 Overall site view 4



July 2007 Overall site view 3



July 2007 Overall site view 2



July 2007 Overall site view 1



July 2007 Excavation work to capping beam in progress (Church side)



July 2007 Concreting to capping beam in progress ( Life style complex side)



July 2007 Installation of king post in progress



July 2007 Fixing of rebar to the capping beam in progress



July 2007 Hacking of pile head for capping beam in progress (Galle road side)



July 2007 Installation of King post in progress



July 2007 Hacking of CBP head for capping beam in progress



July 2007 Excavation work to capping beam in progress



July 2007 Fixing of formwork to capping beam in progress (Life style complex side)



July 2007 Boring work to installation of king post in progress



July 2007 Fixing of rebar to capping beam in progress (Life style complex side)



July 2007 View of constructed capping beam at Tennis court side



July 2007 Fixing of rebar to the capping beam in progress (Life Style Angsana side)



July 2007 Dismantling of formwork to the capping beam in progress (Tennis Court side)



July 2007 Concreting to Capping beam in progress (Tennis court side)



July 2007 Preparation work for lean concrete to the capping beam in progress (Life style angsana side)



July 2007 Rebar work to capping beam in progress



July 2007 Fixing of formwork to Capping beam in progress



July 2007 Static load test to the foundation pile is in progress



June 2007 Overall view 4



June 2007 Overall view 3



June 2007 Overall view 2



June 2007 Overall view 1



June 2007 Temporary hoarding work in progress (Church Side)



June 2007 PDA test to foundation pile in progress



June 2007 Formwork to capping beam in progress (Tennis court side)



June 2007 Rebar work to capping beam in progress (Angsana complex side)



June 2007 Hacking of CBP pile head in progress (Angsana complex side)



June 2007 Rebar work to capping in progress (Tennis court side)



June 2007 Hacking of Pile head in progress for Capping Beam (Tennis court )



June 2007 Preparation work for lean concrete to the pile head in progress



June 2007 Lean concrete to pile head in progress (life style angsana side)



June 2007 View of lean concrete to the Capping beam (Tennis court side)



June 2007 Fabrication of formwork for Capping Beam in progress (Tennis court side)



June 2007 Installation of trimmie pipe for the concreting



June 2007 Static load test in progress to Pile No. P194



June 2007 Inserting of rebar cage to the bore hole (CBP) in progress



June 2007 Formwork in progress to Capping beam build up pile



June 2007 Brick work to build up (CBP pile) pile in progress



June 2007 Boring work to CBP Pile in progress (Angsana complex side)



June 2007 Loading of Kentledge block for static load test in progress (P194)



June 2007 Preparation work in progress for Static Load test (Pile 194)



June 2007 Hacking of pile head to Capping Beam in progress (Angsana side)



June 2007 Hacking of Pile head to Capping Beam in progress (Tennis Court side)



June 2007 Hacking of pile head for capping beam in progress (Tennis court side)



June 2007 Boring work to working pile in progress



June 2007 Excavation work to Capping Beam in progress ( Angsana complex side)



June 2007 Excavation work to capping beam in progress (Tennis court side)



June 2007 Excavation work to Capping Beam in progress (Tennis Court side)



May 2007 Site View 4



May 2007 Site View 3



May 2007 Site View 2



May 2007 Site View 1



May 2007 Boring work to CBP wall in progress (Near to Site main entrance)