Date |
Description |
View |
| |
|
|
|
May 2005
|
Erection of Tower Crane using 25ton Mobil Crane parked at 2 nd storey in progress. |
|
|
May 2005
|
The front Jib of Tower Crane is being lifted using Mobile Crane. |
|
|
May 2005
|
Fixing rebar for Beam & Slab is being carried out at 3 rd storey ( Tower Block ) |
|
|
May 2005
|
The Carpenters are very busy running to complete the remaining beams & slab formwork to hand over to steel fixers. |
|
|
May 2005
|
Erection of form work at 3 rd storey are completed in partial. |
|
|
May 2005
|
Consultants and SPACE`staffs are carrying out joint inspection the outstanding safety items which have been rectified. |
|
|
May 2005
|
The construction joint of Beams and Slab at 3 rd storey slab is properly done. |
|
|
May 2005
|
Local and Foreign Erector are busy running to complete their work before Sun-set so that heavy equipments/materials to handle safely. |
|
|
May 2005
|
Electrical Conduit pipes are laied as per drawing accordingly at 3 rd Storey Slab. |
|
|
May 2005
|
The carpenters are doing erection of formwork for service-lift and core-wall. |
|