Date |
Description |
View |
| |
|
|
|
September 2006
|
Fixing of Aluminium frames are in progress at 19th sty |
|
|
September 2006
|
Timber flooring has been started at 6th sty |
|
|
September 2006
|
The tiling works of bath2 has been started at 6th sty and completed on 4 units. |
|
|
September 2006
|
Overall work progress at View ( A ) |
|
|
September 2006
|
Overall work progress at View ( B ) |
|
|
September 2006
|
Overall work progress at View ( C ) |
|
|
September 2006
|
Overall work progress at View ( D ) |
|
|
October 2006
|
The 27th sty sector A slab cast is completed and erection of wall rebar is in progress. Project Engineer of Singapore pilling is inspecting the rebar prior to closing up the form work |
|
|
October 2006
|
Form work of 27th sty sector B slab is in progress |
|
|
October 2006
|
Casting of swimming pool base slab has been completed and curing of the concrete is in progress |
|
|
October 2006
|
Rebar work of the swimming pool upper deck is in progress |
|
|
October 2006
|
Casting of stair case 1 core wall has been completed from 26th sty to 27th sty |
|
|
October 2006
|
Casting of stair case2 core wall has been completed from 27th sty to 28th sty and erection of rebar and form work from 29th to 30th sty is in progress |
|
|
October 2006
|
Block work is now at 23rd sty |
|
|
October 2006
|
Skim coat application is in progress at 20th sty. |
|
|
October 2006
|
Installation of stair case 1 hand railing has been started and completed up to 19th sty. |
|
|
October 2006
|
Installation of louver window at S1 stair case has been started |
|
|
October 2006
|
Electrical conducting and wiring work is in progress |
|
|
October 2006
|
Overall work progress at View ( A ) |
|
|
October 2006
|
Overall work progress at View ( B ) |
|
|
October 2006
|
Overall work progress at View ( C ) |
|
|
October 2006
|
Overall work progress at View ( D ) |
|
|
November 2006
|
Casting of 29th sty sector A slab has been completed and erection of column & wall form works is in progress |
|
|
November 2006
|
From work of 29th sty sector B slab is in progress. |
|