Date
Description
View
     
September 2006
Fixing of Aluminium frames are in progress at 19th sty
September 2006
Timber flooring has been started at 6th sty
September 2006
The tiling works of bath2 has been started at 6th sty and completed on 4 units.
September 2006
Overall work progress at View ( A )
September 2006
Overall work progress at View ( B )
September 2006
Overall work progress at View ( C )
September 2006
Overall work progress at View ( D )
October 2006
The 27th sty sector A slab cast is completed and erection of wall rebar is in progress. Project Engineer of Singapore pilling is inspecting the rebar prior to closing up the form work
October 2006
Form work of 27th sty sector B slab is in progress
October 2006
Casting of swimming pool base slab has been completed and curing of the concrete is in progress
October 2006
Rebar work of the swimming pool upper deck is in progress
October 2006
Casting of stair case 1 core wall has been completed from 26th sty to 27th sty
October 2006
Casting of stair case2 core wall has been completed from 27th sty to 28th sty and erection of rebar and form work from 29th to 30th sty is in progress
October 2006
Block work is now at 23rd sty
October 2006
Skim coat application is in progress at 20th sty.
October 2006
Installation of stair case 1 hand railing has been started and completed up to 19th sty.
October 2006
Installation of louver window at S1 stair case has been started
October 2006
Electrical conducting and wiring work is in progress
October 2006
Overall work progress at View ( A )
October 2006
Overall work progress at View ( B )
October 2006
Overall work progress at View ( C )
October 2006
Overall work progress at View ( D )
November 2006
Casting of 29th sty sector A slab has been completed and erection of column & wall form works is in progress
November 2006
From work of 29th sty sector B slab is in progress.