Date
Description
View
     
November 2006
Casting of service lift walls has been completed from 28th sty to 29th sty.
November 2006
Casting of passenger lift walls has been completed from 28th sty to 29th sty.
November 2006
After casting the stair case2 core walls up to roof level the doka vertical form work has been dismantled and transferred to the yard.
November 2006
Skim coat application is in progress at 21st sty
November 2006
External plastering work has been started and now in progress on S1 walls & balcony areas.
November 2006
Marble work is in progress at 6th sty and prior to start the fixing dry laying has arranged for the consultant approval.
November 2006
Installation of sliding doors has been started.
November 2006
Installation of curtain wall mullions & transons is in progress.Cw2 has been completed up to 21st sty.
November 2006
Fabrication & installation of fire service lines are in progress at 22nd sty.
November 2006
Overall work progress at View ( A )
November 2006
Overall work progress at View ( B )
November 2006
Overall work progress at View ( C )
November 2006
Overall work progress at View ( D )
December 2006
Roof sector A slab has been cast & casting of RC kerbs & stump columns are in progress
December 2006
Rebar work on roof sector B slab is in progress
December 2006
Passenger lift walls have been cast up to lift motor room slab.
December 2006
Casting of stair case2 steps is completed up to roof slab.
December 2006
Casting service lift core walls has been completed and Doka vertical form work has been dismantled and transferred to the elephant house yard.
December 2006
Form work of stair case1 steps from 30th to roof slab is in progress.
December 2006
Dismantling of swimming pool formwork has been completed and clearing up the 2nd sty is in progress.
December 2006
2 Plinths were cast at 2nd storey in order to place the Generators.