Date |
Description |
View |
| |
|
|
|
December 2006
|
I beam fabrication for transformer room at basement 1 is in progress. |
|
|
December 2006
|
Door sub frames are being fixed at 25th storey. |
|
|
December 2006
|
Timber flooring work is in progress at 10th floor. |
|
|
December 2006
|
Marble work is in progress at 9th storey. |
|
|
December 2006
|
Tiling work is in progress at 10th storey.
Tiling work is in progress at 10th storey. |
|
|
December 2006
|
Electrical testing (Megger test) is being carried out at 20th storey. |
|
|
December 2006
|
Fabrication & installation of fire service lines are in progress at 27th sty.
. |
|
|
December 2006
|
Overall work progress at View ( A ) |
|
|
December 2006
|
Overall work progress at View ( B ) |
|
|
December 2006
|
Overall work progress at View ( C ) |
|
|
December 2006
|
Overall work progress at View ( D ) |
|
|
January 2007
|
Pump house slab, Service Lift Motor room slab has been cast on roof top. |
|
|
January 2007
|
Topping up ceremony was held on 25/01/2007. |
|
|
January 2007
|
Tower crane was dismantled and was sent to the Elephant house yard. |
|
|
January 2007
|
A new derrick crane was installed on roof slab after dismantling tower crane. |
|
|
January 2007
|
Two generators were placed at second storey. |
|
|
January 2007
|
I beam frame for the transformers has been completed at the basement. |
|
|
January 2007
|
Refuse chute has been completed up to 25th storey. |
|
|
January 2007
|
Block work is in progress at 28th storey. |
|
|
January 2007
|
Closing up Ceilings has been started and now in progress at 8th storey. |
|
|
January 2007
|
Plastering and skim coat application are in progress at 25th storey. |
|
|
January 2007
|
Fabrication & Installation of Kitchen cabinet is in progress at 6th storey |
|
|
January 2007
|
Timber flooring work is in progress at 19th floor. |
|
|
January 2007
|
Marble work is in progress at 11th storey. |
|