Date |
Description |
View |
| |
|
|
|
February 2007
|
Casting of passenger lift motor room roof slab has been completed. |
|
|
February 2007
|
Casting of service lift motor room roof slab has been completed and form work of upper roof beams are now in progress. |
|
|
February 2007
|
Installation of bolts for the Gondola brackets is in progress prior to the casting of the columns. |
|
|
February 2007
|
Water proofing and screeding on one sector of the roof slab has been completed. Preparation work for the second sector is now in progress. |
|
|
February 2007
|
Fabrication of the upper roof steel structure is now in progress. |
|
|
February 2007
|
Materials for the passenger lift have been received and part of them is securely stacked at the 2nd storey. |
|
|
February 2007
|
Block work is in progress at 30th sty. |
|
|
February 2007
|
External plastering work is in progress. S1 core walls, A2 unit, W13 wall & W14 wall has been completed up to 19th sty. |
|
|
February 2007
|
Installation of door panels has been started and now in progress at 23rd sty. |
|
|
February 2007
|
Closing up of the ceiling has been started and now it is in progress at 9th sty. |
|
|
February 2007
|
Installation of curtain wall mullions & transons is in progress.Cw2 has been completed up to 28th sty. |
|
|
February 2007
|
Marble work now in progress at 15th sty. |
|
|
February 2007
|
Timber flooring has been completed up to 19th sty. |
|
|
February 2007
|
Fabrication of the entrance door timber paneling has been started and completed up to 10th sty. |
|
|
February 2007
|
Overall work progress at View ( A ) |
|
|
February 2007
|
Overall work progress at View ( B ) |
|
|
February 2007
|
Overall work progress at View ( C ) |
|
|
February 2007
|
Overall work progress at View ( D ) |
|
|
March 2007
|
Casting of upper roof RC beams has been completed and the installations of steel beams are now in progress. |
|
|
March 2007
|
80% of the Gondola stumps has been cast and remaining to be complete by second week of April. |
|
|
March 2007
|
Excavation of trenches for the water tank plinths is in progress. Prior to start the work at 1st sty SP had put up hording to close up the area. |
|
|
March 2007
|
Construction of the fuel tank room at basement 1 has been started. All the existing partition walls were demolished on that area and the form work of the RC beam is in progress. |
|
|
March 2007
|
Plinths for the Domus lifts have been cast on 29th sty. Installation of Domus lifts to be start immediately after the completion of the plastering on the surrounding walls. |
|
|
March 2007
|
Brick walls on the Passenger & Service lift motor rooms were completed and the plastering is now in progress prior to start installation of motors. |
|