February 2007
Casting of passenger lift motor room roof slab has been completed.
February 2007
Casting of service lift motor room roof slab has been completed and form work of upper roof beams are now in progress.
February 2007
Installation of bolts for the Gondola brackets is in progress prior to the casting of the columns.
February 2007
Water proofing and screeding on one sector of the roof slab has been completed. Preparation work for the second sector is now in progress.
February 2007
Fabrication of the upper roof steel structure is now in progress.
February 2007
Materials for the passenger lift have been received and part of them is securely stacked at the 2nd storey.
February 2007
Block work is in progress at 30th sty.
February 2007
External plastering work is in progress. S1 core walls, A2 unit, W13 wall & W14 wall has been completed up to 19th sty.
February 2007
Installation of door panels has been started and now in progress at 23rd sty.
February 2007
Closing up of the ceiling has been started and now it is in progress at 9th sty.
February 2007
Installation of curtain wall mullions & transons is in progress.Cw2 has been completed up to 28th sty.
February 2007
Marble work now in progress at 15th sty.
February 2007
Timber flooring has been completed up to 19th sty.
February 2007
Fabrication of the entrance door timber paneling has been started and completed up to 10th sty.
February 2007
Overall work progress at View ( A )
February 2007
Overall work progress at View ( B )
February 2007
Overall work progress at View ( C )
February 2007
Overall work progress at View ( D )
March 2007
Casting of upper roof RC beams has been completed and the installations of steel beams are now in progress.
March 2007
80% of the Gondola stumps has been cast and remaining to be complete by second week of April.
March 2007
Excavation of trenches for the water tank plinths is in progress. Prior to start the work at 1st sty SP had put up hording to close up the area.
March 2007
Construction of the fuel tank room at basement 1 has been started. All the existing partition walls were demolished on that area and the form work of the RC beam is in progress.
March 2007
Plinths for the Domus lifts have been cast on 29th sty. Installation of Domus lifts to be start immediately after the completion of the plastering on the surrounding walls.
March 2007
Brick walls on the Passenger & Service lift motor rooms were completed and the plastering is now in progress prior to start installation of motors.