Date |
Description |
View |
| |
|
|
|
March 2007
|
Internal Plastering is in progress at 28th sty |
|
|
March 2007
|
Painting work has been started. |
|
|
March 2007
|
Application of the wall putty has been started from 7th sty B3 unit. |
|
|
March 2007
|
Installation of both S1 & S2 louvers has been almost competed. |
|
|
March 2007
|
Installation of Kitchen cabinet is in progress at 17th sty. |
|
|
March 2007
|
External plastering on the surrounding walls of A2 unit & S1 core walls has been completed up to roof level. |
|
|
March 2007
|
Erection of scaffolding for the service lift has been completed and installation of guide rail brackets is now in progress. |
|
|
March 2007
|
Overall work progress at View ( A ) |
|
|
March 2007
|
Overall work progress at View ( B ) |
|
|
March 2007
|
Overall work progress at View ( C ) |
|
|
March 2007
|
Overall work progress at View ( D ) |
|
|
April 2007
|
Form work and rebar work of the car park has been started |
|
|
April 2007
|
Rebar work of the one part of the 1st sty water tank beams has been completed and the form work is now in progress. |
|
|
April 2007
|
Application of the water proofing on the second sector of the roof slab has been completed and the ponding test is now in progress. |
|
|
April 2007
|
Fabrication & Installation of the main steel frame of the two upper roofs has been completed. |
|
|
April 2007
|
Installation of the water tank on the roof slab has been completed. |
|
|
April 2007
|
Erection of the steel columns of the trellis roof at the roof slab is in progress. |
|
|
April 2007
|
Installation of the guide rails of the service lift has been completed and the installation of door frame is now in progress. |
|
|
April 2007
|
Fabrication & Installation of the fuel tank supporting frame has been completed and waiting for the installation of the tanks to complete the balance block walls. |
|
|
April 2007
|
External paining around the A2 unit has been completed from 19th sty below. So schedule to start the dismantling the external scaffolding by first week of May. |
|
|
April 2007
|
Installation of A2 A/C ledge lower completed up to 22nd sty. |
|
|
April 2007
|
Installation of the hand rails on both stair cases has been completed up to roof. |
|
|
April 2007
|
Fixing the bath room fittings on the 7th & 8th sty B3 units are in progress. |
|
|
April 2007
|
Fixing of door panels is now in progress at 28th sty. |
|