Date
Description
View
     
March 2007
Internal Plastering is in progress at 28th sty
March 2007
Painting work has been started.
March 2007
Application of the wall putty has been started from 7th sty B3 unit.
March 2007
Installation of both S1 & S2 louvers has been almost competed.
March 2007
Installation of Kitchen cabinet is in progress at 17th sty.
March 2007
External plastering on the surrounding walls of A2 unit & S1 core walls has been completed up to roof level.
March 2007
Erection of scaffolding for the service lift has been completed and installation of guide rail brackets is now in progress.
March 2007
Overall work progress at View ( A )
March 2007
Overall work progress at View ( B )
March 2007
Overall work progress at View ( C )
March 2007
Overall work progress at View ( D )
April 2007
Form work and rebar work of the car park has been started
April 2007
Rebar work of the one part of the 1st sty water tank beams has been completed and the form work is now in progress.
April 2007
Application of the water proofing on the second sector of the roof slab has been completed and the ponding test is now in progress.
April 2007
Fabrication & Installation of the main steel frame of the two upper roofs has been completed.
April 2007
Installation of the water tank on the roof slab has been completed.
April 2007
Erection of the steel columns of the trellis roof at the roof slab is in progress.
April 2007
Installation of the guide rails of the service lift has been completed and the installation of door frame is now in progress.
April 2007
Fabrication & Installation of the fuel tank supporting frame has been completed and waiting for the installation of the tanks to complete the balance block walls.
April 2007
External paining around the A2 unit has been completed from 19th sty below. So schedule to start the dismantling the external scaffolding by first week of May.
April 2007
Installation of A2 A/C ledge lower completed up to 22nd sty.
April 2007
Installation of the hand rails on both stair cases has been completed up to roof.
April 2007
Fixing the bath room fittings on the 7th & 8th sty B3 units are in progress.
April 2007
Fixing of door panels is now in progress at 28th sty.