Date |
Description |
View |
| |
|
|
|
April 2007
|
Overall Work Progress at View ( A ) |
|
|
April 2007
|
Overall Work Progress at View ( B ) |
|
|
April 2007
|
Overall Work Progress at View ( C ) |
|
|
April 2007
|
Overall Work Progress at View ( D ) |
|
|
May 2007
|
Casting the one section of 6th sty void has been done and the form work of the second part is now in progress. |
|
|
May 2007
|
RC beams of one of the water tank at 1st sty have been cast and the rebar work of the beams of the second water tank is now in progress. |
|
|
May 2007
|
Service lift lobby and the stair case at 2nd sty have been cast. |
|
|
May 2007
|
Form work and rebar work of stair case 2 from 2nd sty to 5th sty is now in progress. |
|
|
May 2007
|
Construction of the 3rd sty car park has resume back and already cast one part of it. |
|
|
May 2007
|
About 60% of the water proofing work of the roof terrace has been completed and remaining is schedule to finish before the dismantling of the derrick crane. |
|
|
May 2007
|
Installation of the Service lift cart has been done and commissioning is now in progress. |
|
|
May 2007
|
Installation of the Attenuator ducts and exhaust pipes of the Generators are now in progress. |
|
|
May 2007
|
External finishes around the A2 unit, A3 unit & S1 core walls have been completed. So the dismantling of the external scaffolding of those areas is now in progress. |
|
|
May 2007
|
Block walls of the tower block is almost completed except the partition wall of the MB & BR2 on B2 unit |
|
|
May 2007
|
Polishing of the timber flooring is now in progress. |
|
|
May 2007
|
Installation of sanitary & electrical fittings is in progress at 5th & 6th stories. |
|
|
May 2007
|
Tilling on corridors has been started and now it’s in progress at 6th sty. |
|
|
May 2007
|
Installation of the furniture on 7th & 8th sty B3 units has been done. |
|
|
May 2007
|
Overall Work Progress at View ( A ) |
|
|
May 2007
|
Overall Work Progress at View ( B ) |
|
|
May 2007
|
Overall Work Progress at View ( C ) |
|
|
May 2007
|
Overall Work Progress at View ( D ) |
|
|
June 2007
|
Form work of the pump house roof slab has been started and schedule to cast first week of next month. |
|
|
June 2007
|
Form work and rebar work of the 3rd sty car park ramp area is now in progress. |
|