April 2007
Overall Work Progress at View ( A )
April 2007
Overall Work Progress at View ( B )
April 2007
Overall Work Progress at View ( C )
April 2007
Overall Work Progress at View ( D )
May 2007
Casting the one section of 6th sty void has been done and the form work of the second part is now in progress.
May 2007
RC beams of one of the water tank at 1st sty have been cast and the rebar work of the beams of the second water tank is now in progress.
May 2007
Service lift lobby and the stair case at 2nd sty have been cast.
May 2007
Form work and rebar work of stair case 2 from 2nd sty to 5th sty is now in progress.
May 2007
Construction of the 3rd sty car park has resume back and already cast one part of it.
May 2007
About 60% of the water proofing work of the roof terrace has been completed and remaining is schedule to finish before the dismantling of the derrick crane.
May 2007
Installation of the Service lift cart has been done and commissioning is now in progress.
May 2007
Installation of the Attenuator ducts and exhaust pipes of the Generators are now in progress.
May 2007
External finishes around the A2 unit, A3 unit & S1 core walls have been completed. So the dismantling of the external scaffolding of those areas is now in progress.
May 2007
Block walls of the tower block is almost completed except the partition wall of the MB & BR2 on B2 unit
May 2007
Polishing of the timber flooring is now in progress.
May 2007
Installation of sanitary & electrical fittings is in progress at 5th & 6th stories.
May 2007
Tilling on corridors has been started and now it’s in progress at 6th sty.
May 2007
Installation of the furniture on 7th & 8th sty B3 units has been done.
May 2007
Overall Work Progress at View ( A )
May 2007
Overall Work Progress at View ( B )
May 2007
Overall Work Progress at View ( C )
May 2007
Overall Work Progress at View ( D )
June 2007
Form work of the pump house roof slab has been started and schedule to cast first week of next month.
June 2007
Form work and rebar work of the 3rd sty car park ramp area is now in progress.