Date
Description
View
     
June 2007
Dismantling of derrick crane 2 has been started and schedules to complete it by the first week of July.
June 2007
Installation of the two water tanks at 1st sty is now in progress.
June 2007
Installation of the domus lifts are now in progress.
June 2007
Primer application on the swimming pool upper deck and the main pool has been done prior to the sheet application.
June 2007
Form work of the slab over of the stair case 1 from 3rd sty to 5th sty is now in progress.
June 2007
Rendering of the stair case 1 has been started and already completed up to 26th sty.
June 2007
Floor tilling on the roof terrace is in progress.
June 2007
Polishing of the timber flooring is now in progress.
June 2007
Installation of sanitary & electrical fittings is in progress at 5th & 6th stories.
June 2007
Installation of the passenger lift door jams has been started.
June 2007
Installation of pumps at sprinkler pump room has been done and the piping is now in progress.
June 2007
Overall Work Progress at View ( A )
June 2007
Overall Work Progress at View ( B )
June 2007
Overall Work Progress at View ( C )
June 2007
Overall Work Progress at View ( D )
july 2007
Form work of car park ramp from 2nd sty to 3rd sty is now in progress and schedule to cast by first week of August.
july 2007
Casting of stair case 3 has been completed up to 2nd sty level.
july 2007
Main steel framing of the trellis roof above the cooling tower is almost completed.
july 2007
Demolished the temporary worker toilets at 2nd sty and form work is now in progress to cast back the opening.
july 2007
Installation of the main framing, cabin & jack of the Domus lifts at units PS1 & PS2 are completed.
july 2007
Testing and commissioning of the service lift has been done and now it serving for the site work.
july 2007
About 70% of the piping work of the roof water tank is completed and installation of one water tank out of the two at 1st sty is also completed
july 2007
Installation of the 3 passenger lifts is almost completed and one is already serving for the site work.

Page 01-02-03-04-05-06-07-08-09-10-11-12-13-14-15-16-17-18-19-20