June 2007
|
Dismantling of derrick crane 2 has been started and schedules to complete it by the first week of July. |
|
|
June 2007
|
Installation of the two water tanks at 1st sty is now in progress. |
|
|
June 2007
|
Installation of the domus lifts are now in progress. |
|
|
June 2007
|
Primer application on the swimming pool upper deck and the main pool has been done prior to the sheet application. |
|
|
June 2007
|
Form work of the slab over of the stair case 1 from 3rd sty to 5th sty is now in progress. |
|
|
June 2007
|
Rendering of the stair case 1 has been started and already completed up to 26th sty. |
|
|
June 2007
|
Floor tilling on the roof terrace is in progress. |
|
|
June 2007
|
Polishing of the timber flooring is now in progress. |
|
|
June 2007
|
Installation of sanitary & electrical fittings is in progress at 5th & 6th stories. |
|
|
June 2007
|
Installation of the passenger lift door jams has been started. |
|
|
June 2007
|
Installation of pumps at sprinkler pump room has been done and the piping is now in progress. |
|
|
June 2007
|
Overall Work Progress at View ( A ) |
|
|
June 2007
|
Overall Work Progress at View ( B ) |
|
|
June 2007
|
Overall Work Progress at View ( C ) |
|
|
June 2007
|
Overall Work Progress at View ( D ) |
|
|
july 2007
|
Form work of car park ramp from 2nd sty to 3rd sty is now in progress and schedule to cast by first week of August. |
|
|
july 2007
|
Casting of stair case 3 has been completed up to 2nd sty level. |
|
|
july 2007
|
Main steel framing of the trellis roof above the cooling tower is almost completed. |
|
|
july 2007
|
Demolished the temporary worker toilets at 2nd sty and form work is now in progress to cast back the opening. |
|
|
july 2007
|
Installation of the main framing, cabin & jack of the Domus lifts at units PS1 & PS2 are completed. |
|
|
july 2007
|
Testing and commissioning of the service lift has been done and now it serving for the site work. |
|
|
july 2007
|
About 70% of the piping work of the roof water tank is completed and installation of one water tank out of the two at 1st sty is also completed |
|
|
july 2007
|
Installation of the 3 passenger lifts is almost completed and one is already serving for the site work. |
|