Date |
Description |
View |
| |
|
|
|
july 2007
|
7th sty corridor and two lift lobbies have been fully completed by SPACE as a mock up. Here Mr. Stephan from AHPL is inspecting the finishes. |
|
|
july 2007
|
Aluminum louvers at 2nd sty have been started. |
|
|
july 2007
|
Fixing the composite panels on the two upper roofs is now in progress and schedule to start the glass fixing by mid of August. |
|
|
july 2007
|
The final finishing looks of a fully completed corridor with the light switch on |
|
|
july 2007
|
Overall Work Progress at View ( A ) |
|
|
july 2007
|
Overall Work Progress at View ( B ) |
|
|
july 2007
|
Overall Work Progress at View ( C ) |
|
|
july 2007
|
Overall Work Progress at View ( D ) |
|
|
September 2007
|
The two upper roofs are almost completed |
|
|
September 2007
|
Capping work of the trellis roof on the roof top is now in progress. |
|
|
September 2007
|
About 90% of the floor finishing has been completed on the roof slab. |
|
|
September 2007
|
Installation of the steel stair cases on PS units at 29th sty is now in progress and schedule to complete all 4 stair cases by 21/10/07. |
|
|
September 2007
|
Installation of glass panels of the sky lights on the roof top has been completed. |
|
|
September 2007
|
Final finishing look of a passenger lift. |
|
|
September 2007
|
Installation of the Domus lift at unit PS1 is fully completed except testing and commissioning. |
|
|
September 2007
|
Tilling work of the swimming pool is now in progress. |
|
|
September 2007
|
Texture paint of the 2nd sty soffit has been started and schedules to complete both floors by 20/10/07. |
|
|
September 2007
|
Tilling work of the B2, B1, 1st sty, 2nd sty & 3rd sty lift lobbies has been almost completed. |
|
|
September 2007
|
Works in the facility rooms at 3rd sty are also in progress. |
|
|
September 2007
|
Glass railing on the swimming pool has been completed. |
|
|
September 2007
|
Water tank piping work of the roof top has been fully completed. |
|
|
September 2007
|
Electrical wiring ,trunking & fire protection piping at 2nd sty is almost completed. |
|
|
September 2007
|
Overall Work Progress at View ( A ) |
|
|
September 2007
|
Overall Work Progress at View ( B ) |
|