September 2007
Overall Work Progress at View ( D )
October 2007
Concrete wall for the main signage has been cast
October 2007
Grind the 2nd sty floor slab to make the surface good has been almost completed
October 2007
Cladding work and fixing the glasses on the 3rd sty glass roofing is in progress
October 2007
Gondola is now using to replace the damaged glasses on the curtain walls
October 2007
Alum trellis roof above the cooling tower is fully completed
October 2007
Hacking work to construct the new driveway is now in progress
October 2007
Architectural finishing work at roof terrace is almost completed
October 2007
About 70% of the tilling work has been completed at the swimming pool
October 2007
Internal capping work of the unit B2 side curtain wall is now in progress
October 2007
Finishing work of the unit B2 has been started and already handed over 7, 8 & 9 sty unit B2 for architectural inspection
October 2007
Ceiling grids at the 3rd sty facility rooms has been done and waiting for M&E clearance to close up the ceiling
October 2007
Corridors have been completed up to 12th sty and progressively finishing other floors as well
October 2007
MSB has turned on & energized the bus bar, main DB’s from 5th to 20th sty. Here the client is inspecting the MSB when the turning on
October 2007
Photo that shows the building at night time with light switched on
October 2007
Overall Work Progress at View ( A )
October 2007
Overall Work Progress at View ( B )
October 2007
Overall Work Progress at View ( C )
October 2007
Overall Work Progress at View ( D )