Date |
Description |
View |
| |
|
|
|
September 2007
|
Overall Work Progress at View ( D ) |
|
|
October 2007
|
Concrete wall for the main signage has been cast |
|
|
October 2007
|
Grind the 2nd sty floor slab to make the surface good has been almost completed |
|
|
October 2007
|
Cladding work and fixing the glasses on the 3rd sty glass roofing is in progress |
|
|
October 2007
|
Gondola is now using to replace the damaged glasses on the curtain walls |
|
|
October 2007
|
Alum trellis roof above the cooling tower is fully completed |
|
|
October 2007
|
Hacking work to construct the new driveway is now in progress |
|
|
October 2007
|
Architectural finishing work at roof terrace is almost completed |
|
|
October 2007
|
About 70% of the tilling work has been completed at the swimming pool |
|
|
October 2007
|
Internal capping work of the unit B2 side curtain wall is now in progress |
|
|
October 2007
|
Finishing work of the unit B2 has been started and already handed over 7, 8 & 9 sty unit B2 for architectural inspection |
|
|
October 2007
|
Ceiling grids at the 3rd sty facility rooms has been done and waiting for M&E clearance to close up the ceiling |
|
|
October 2007
|
Corridors have been completed up to 12th sty and progressively finishing other floors as well |
|
|
October 2007
|
MSB has turned on & energized the bus bar, main DB’s from 5th to 20th sty. Here the client is inspecting the MSB when the turning on |
|
|
October 2007
|
Photo that shows the building at night time with light switched on |
|
|
October 2007
|
Overall Work Progress at View ( A ) |
|
|
October 2007
|
Overall Work Progress at View ( B ) |
|
|
October 2007
|
Overall Work Progress at View ( C ) |
|
|
October 2007
|
Overall Work Progress at View ( D ) |
|