May 2005
All columns of 3 rd sty at Sectot ”B” completed and formwork and rebar work leading to 3 rd sty in progress.
May 2005
The M&E Workers are doing installation of pipe sleeve for plumbing & sanitary and laying conduits for electrical works.
July 2005
Casting of 3rd sty Podium ( Car-Park ) Slab in Progress
July 2005
Construction Joints at beams and slab are properly placed using hyrib material with proper support.
July 2005
The Concrete Pump is pouring concrete to the Column Cap at CB-13 of Sector “A “ at Transfer Plate.
July 2005
The Surveyor is doing setting out lines for Stair-Case “1” and some other grid lines at 3rd sty Slab.
July 2005
Casting of Plinths for Coling Tower at 2nd Sty is being done.
July 2005
Laying of Electrical Conduit of new mail box area at 3rd sty slab is in progress.
July 2005
Erection of formwork for slab recess area due to M&E Services is completed at Sector “A” of Transfer Plate.
July 2005
Internal Scaffolding are being erected according to the temporary work designed and P.E will inspect internal/cantilever platform before 1st cast of Transfer Plate.
July 2005
Column Starter bar ( Type: C3 ), have been planted next to M&E pipe sleeves as per approved drawings.
July 2005
Bottom reinforcement at slab recess area of Sector “A” has been completed.
July 2005
Formwork erection of Sector “C” is partially completed and Supervisor is using level instrument to check formwork is correct within tolerance.
July 2005
The removal of loose concrete is being done at Column cap before laying of reinforcement at Transfer Plate.
July 2005
Preparation work for UB installation of temporary cantilever platform next to Service Lift at 3rd sty in progress.
July 2005
Rebar, formwork & casting of columns at Swimming Pool area in progress.
July 2005
Testing Specialist is doing UPV test of CB-10 at 2nd Sty witness by Prof: Dr. Dias, Mr. Stephan & Mr.Dillip of AHPL, Mr.Kumudu & Mr. Indrajith of PA and SPACE Staffs.
July 2005
Prof: Dr. Dias is recording the readings from UPV Test for his analysis for quality of Concrete.