August 2005
|
Mr.Soh of P&T Consultants, Mr.Stephan of AHPL, Prof: Dr.Dias and SPACE` Staffs are holding a meeting, in regard to Concrete Quality Control as it is very important to Structural Integrity |
|
|
August 2005
|
The Consultants, SPACE and all other trades are attending for their headcount at assembly point when they hear warning sound ( siren ) as a Fire and Emergency Evacuation exercise. |
|
|
August 2005
|
Fine and coarse aggregate are being carried to the hoppers through conveyor belt prior to do sieving at super-mix batching plant prior to pouring concrete of swimming pool deck at 3rd sty. |
|
|
August 2005
|
The Stationary Concrete Pump set up and joining of piping work have been permanently installed at 2nd Sty. |
|
|
August 2005
|
The temporary cantilever platform @ 3rd sty next to Service-Lift is completed for inspection to be carried out by Mr.Foo , to ensure that work done should be the same as per drawings accordingly. |
|
|
August 2005
|
The Surveyor is doing all sort of setting out such as M&E Openings, Columns and Walls position at Sector” C ” of Transfer Plate |
|
|
August 2005
|
The Site Engineer is doing zero setting of prism ( Surveying Equipment ) to do column setting out prior to installation of column starter bar at transfer plate at Sector “C” to be cast on 28-08-05 originally planned. |
|
|
August 2005
|
New Cooling Tower has been completely installed at 2nd Sty and piping work leading to cooling tower in progress. |
|
|
August 2005
|
The erection of staging & formwork are completed in partial at Transfer Plate of Sector” B”. |
|
|
August 2005
|
The installation of main bottom bars at 5th sty of Sector” B” are being laid. |
|
|
August 2005
|
The assembly of cooling tower pipes are being carried out next to new cooling tower which has been entirely erected. |
|
|
August 2005
|
The shear links are being installed at Sector” C “ of Transfer Plate
Which suppose to cast on 28-08-05 ( Sunday ).
|
|
|
August 2005
|
The steel fixers are busy running to complete top reinforcement for 1st layer of cast at Sector “ C “ of Transfer Plate as per schedule originally planned. |
|
|
August 2005
|
The wall starter bars at Stair-case “2” have been completely installed accordingly to Architectural Setting out dimension done by Our Surveyor. |
|
|
August 2005
|
The formwork and main reinforcement have been done and are ready for pouring concrete at Transfer Plate ( Sector “C” ) |
|
|
August 2005
|
R.C Columns, beams & slab at swimming pool deck are cast in partial. |
|
|
August 2005
|
The erection of staging and formwork for entire Transfer Plate are being installed as per P.E design.( 90% completed. ) |
|
|
August 2005
|
The M&E workers are using temporary removable scaffold with safety checklist inspected and approved by Safety Officer to do electrical wiring through cast in conduit at 3rd sty slab of Tower Block |
|
|
August 2005
|
Seen temporary scaffolding barricaded with green safety net at Transfer Plate which is ready for casting upon approval of Consultants. |
|
|
August 2005
|
Mr.Khin, Project Engineer of SPACE is doing a check for column setting out as it is very important to suit Architectural Layout before commencement of pouring concrete at Transfer Plate. |
|
|
September 2005
|
Cleanliness is being carried out before conducting final inspection with Consultants prior to casting at 2nd layer of Section “A” |
|
|
September 2005
|
Pouring of Concrete at 2nd Layer of Sector ”A“ is in progress. |
|