Date |
Description |
View |
| |
|
|
|
September 2005
|
80% of laying top reinforcement T-1, T-2, T-3 & T-4 ( four layers ) are completed at Sector” A “. |
|
|
Sptember 2005
|
Good rough concrete surface is seen after being completed of cleanliness prior to lay top reinforcement at Sector “A” |
|
|
September 2005
|
Fabrication of system column formwork for typical floor are being done. |
|
|
September 2005
|
The final layer cast of Transfer Plate at Sector ”A” in progress. |
|
|
September 2005
|
The steel fixers are busy tying of top reinforcement bar at Sector ”B” Transfer Plate to cast the slab on schedule. |
|
|
September 2005
|
Installation of M&E Pipes connecting to Cooling Tower at B-1 High Level has been completed. |
|
|
September 2005
|
Installation of Cooling Tower & Make up water tank are ready for (T&C ) prior to start operation. |
|
|
September 2005
|
85% of final cast for entire Transfer Plate has been completed. |
|
|
October 2005
|
Erection of wall rebar for strengthening work has been done from Basement -1 to 1st Storey and form work in progress. |
|
|
October 2005
|
Dismantling of staging and formwork of Transfer Plate at Sector “C” has been partially completed, and good quality of concrete surface without having honeycomb is seen. |
|
|
October 2005
|
Proper safe stripping of formwork is being carried out at Sector “A” of Transfer Plate without causing floor damages at 3rd sty which has been done with power float finish. |
|
|
October 2005
|
The Steel fixers are busy rushing to complete the laying of rebar at Sector “B” prior to final cast of entire Transfer Plate. |
|
|
October 2005
|
The cleanliness of 1st cast concrete surface, final touch up work for shear links & columns/walls starter bar before proceeding to erection of top reinforcement bar are being done. |
|
|
October 2005
|
The R.C stair-case walls have been cast by using “ Doka climbing formwork system which gives safe, quick and easy work done during operation one floor to another at any height. |
|
|
October 2005
|
Our Supervisor is doing (as-built ) site measurement of Passenger Lift Shaft after cast, using Doka System formwork, ensuring to achieve structural clear opening with good verticality. |
|
|
October 2005
|
The Service Lift has been cast from 5th to 6th sty and erection of formwork & rebar ( 6th to 7th floor ) are being carried out. |
|
|
October 2005
|
The fabrication of “Aluma Tableform system” for beam and slab (Typical Floor ) which performs the work safely and efficiently is in progress. |
|
|
October 2005
|
Pre-fabrication column is used to expedite the work on site so that we can catch up the cycle time as per schedule. |
|
|
October 2005
|
The new Cooling Tower is now in operation, serving the existing Shopping Mall. |
|
|
October 2005
|
It was found that good quality of concrete without having any defects at Wall W-8 at 6th story after dismantling of formwork |
|
|
October 2005
|
Doka wall form systems, being used are seen with high standards of safety |
|
|
November 2005
|
6th Sty Slab ( Sector-A ) has been cast and Columns setting out lines are being carried out. |
|