Date |
Description |
View |
| |
|
|
|
November 2005
|
Casting G-45N/mm2 concrete at column area using concrete bucket and follow by G-35N/mm2 at beam & slab using concrete pump ( 6th Sty of Sector-B) with compliance to the specification. |
|
|
November 2005
|
Laying of bottom mesh at 6th Sty of Sector-B is being done and installation of electrical conduit is being proceeded as well. |
|
|
November 2005
|
We have provided 150mm drop sunken R.C slab accordingly to the Architectural Layout at Bath, Utilities & Kitchen area. |
|
|
November 2005
|
Seen good quality of concrete at R.C Columns from 6th Sty to 7th Sty without having honeycomb with smooth surface. |
|
|
November 2005
|
HKL Horizontal Table form is being launched at 6th sty slab for preparation work on 7th Sty cast. |
|
|
November 2005
|
Most of the table forms have been erected at Sector(A) & Sector (B) from 6th Sty to 7th Sty. |
|
|
November 2005
|
Dismantling of existing Cooling Tower at 2nd Sty is in progress. |
|
|
November 2005
|
The formwork level and beam sizes are being checked before laying of rebar as to minimize the unnecessary abortive work as well as achieving a good quality control of R.C Work. |
|
|
November 2005
|
The installation of electrical conduit pipes and other M&E Services are being laid after being completed bottom mesh prior to start tying on top bar in order to meet the date cast on schedule. |
|
|
November 2005
|
The horizontal and vertical system formworks with green safety nets provided have already been installed for on-going pouring of concrete. |
|
|
January 2006
|
Erecting of Column reinforcement works of 9th to 10th Sty at Sector A. Doka forms have been climbed up to the next level at Passenger lift & Stair-Case ( 2 ). |
|
|
January 2006
|
R.C Plinths of Existing Cooling Tower have fully been removed except for those of Existing Water-tank which are currently serving to Shopping Mall. |
|
|
January 2006
|
The removal of existing up-stand beams have been done and water proofing work at construction joint is completed as well at Delifrance area. |
|
|
January 2006
|
Removal of Temporary Support Structure (“I” beams ) on Level 3 is in progress. |
|
|
January 2006
|
Professional Engineer has inspected the Hoist Base Structure and erection of Hoist is being carried out By Hoist Specialist(Singapore). |
|
|
January 2006
|
Entire 9th Sty Slab has been cast and concrete curing is properly done for 7 days , especially on exposed surface. |
|
|
January 2006
|
Erection of Formwork at Swimming Pool are is in progress. |
|
|
January 2006
|
Floor Slab Form works are in progress at 9th Sty Slab |
|
|
January 2006
|
Casting of Service Lift at 10th Sty & Stair-case (1) at 9th Sty are completed respectively. |
|
|
January 2006
|
Installation of Column rebar of 9th Sty at Sector “A” is in progress. |
|
|
Ferbuary 2006
|
11th Sty slab has been cast and which is being done curing for ( 7 days ) |
|
|
February 2006
|
The erection of formwork is completed and the bottom mesh is being laid prior to installation of M&E conduit pipe at 2nd half of 11th Sty. |
|
|
February 2006
|
Horizontal System Formworks are seen after being lowered down prior to flying to the next floor. |
|
|
February 2006
|
The setting out dimension is in progress prior to start brick laying at 9th Sty. |
|