Date
Description
View
     
November 2005
Casting G-45N/mm2 concrete at column area using concrete bucket and follow by G-35N/mm2 at beam & slab using concrete pump ( 6th Sty of Sector-B) with compliance to the specification.
November 2005
Laying of bottom mesh at 6th Sty of Sector-B is being done and installation of electrical conduit is being proceeded as well.
November 2005
We have provided 150mm drop sunken R.C slab accordingly to the Architectural Layout at Bath, Utilities & Kitchen area.
November 2005
Seen good quality of concrete at R.C Columns from 6th Sty to 7th Sty without having honeycomb with smooth surface.
November 2005
HKL Horizontal Table form is being launched at 6th sty slab for preparation work on 7th Sty cast.
November 2005
Most of the table forms have been erected at Sector(A) & Sector (B) from 6th Sty to 7th Sty.
November 2005
Dismantling of existing Cooling Tower at 2nd Sty is in progress.
November 2005
The formwork level and beam sizes are being checked before laying of rebar as to minimize the unnecessary abortive work as well as achieving a good quality control of R.C Work.
November 2005
The installation of electrical conduit pipes and other M&E Services are being laid after being completed bottom mesh prior to start tying on top bar in order to meet the date cast on schedule.
November 2005
The horizontal and vertical system formworks with green safety nets provided have already been installed for on-going pouring of concrete.
January 2006
Erecting of Column reinforcement works of 9th to 10th Sty at Sector A. Doka forms have been climbed up to the next level at Passenger lift & Stair-Case ( 2 ).
January 2006
R.C Plinths of Existing Cooling Tower have fully been removed except for those of Existing Water-tank which are currently serving to Shopping Mall.
January 2006
The removal of existing up-stand beams have been done and water proofing work at construction joint is completed as well at Delifrance area.
January 2006
Removal of Temporary Support Structure (“I” beams ) on Level 3 is in progress.
January 2006
Professional Engineer has inspected the Hoist Base Structure and erection of Hoist is being carried out By Hoist Specialist(Singapore).
January 2006
Entire 9th Sty Slab has been cast and concrete curing is properly done for 7 days , especially on exposed surface.
January 2006
Erection of Formwork at Swimming Pool are is in progress.
January 2006
Floor Slab Form works are in progress at 9th Sty Slab
January 2006
Casting of Service Lift at 10th Sty & Stair-case (1) at 9th Sty are completed respectively.
January 2006
Installation of Column rebar of 9th Sty at Sector “A” is in progress.
Ferbuary 2006
11th Sty slab has been cast and which is being done curing for ( 7 days )
February 2006
The erection of formwork is completed and the bottom mesh is being laid prior to installation of M&E conduit pipe at 2nd half of 11th Sty.
February 2006
Horizontal System Formworks are seen after being lowered down prior to flying to the next floor.
February 2006
The setting out dimension is in progress prior to start brick laying at 9th Sty.