Date
Description
View
     
February 2006
The plastering & skim coat are completed and ceiling frame is being installed at Mock Up Unit.
February 2006
The plastering work, skim coat and brick laying are being carried out at 7th Sty.
February 2006
All M&E Services are installed at Mock –Up Unit.
February 2006
Seen proper Mechanical mixing of Skim Coat material for application on Slab Soffit.
February 2006
Overall Work Progress at View (A )
February 2006
Overall Work Progress at View (B )
February 2006
Overall Work Progress at View (C )
February 2006
Overall Work Progress at View (D )
March 2006
The verticality check of Column ( 12 th to 13th Sty ) is being done and witnessed by Consultants before pouring concrete
March 2006
The form work and rebar work are being done as well as laying of M&E pipes at 13th sty of Sector ( A ).
March 2006
The erection of formwork and laying of rebar & M&E service pipes are completed prior to do inspection with Consultants before pouring of concrete at 13th sty of Sector ( B )
March 2006
The erection of formwork at Swimming Pool area in progress.
March 2006
The Plastering work, skim coat and ceiling work at Mock Up Unit Area in progress. The M&E Services are being installed as well.
March 2006
The Aluminum Works have been installed and the tiling Work at Balcony in progress at Mock Up Unit.
March 2006
The brick laying works at lower floor are almost
March 2006
The plastering works at some of the units at 5th, 6th, 7th & 8th sty are completed.
March 2006
The Hoarding Work at Basement-1 has been completed prior to start demolition work & brick laying work as to install Transformer Units
March 2006
The R.C Plinths have been completed for installation of Water Tank and the demolition of existing R.C Columns, Walls & beams have been completed as well.
March 2006
Overall Work Progress at View ( A )

Page 01-02-03-04-05-06-07-08-09-10-11-12-13-14-15-16-17-18-19-20