Date |
Description |
View |
| |
|
|
|
March 2006
|
Overall Work Progress at View ( C ) |
|
|
March 2006
|
Overall Work Progress at View ( D ) |
|
|
Aprial 2006
|
14th sty slab has been cast at (Sector-A) and curing is being carried out for (7-days). |
|
|
Aprial 2006
|
Some of columns from 14th to 15th sty have been cast and the offset level to the floor is being marked for reference during construction activities. |
|
|
Aprial 2006
|
The cleanliness is completely done and the survey setting out for Architectural Work is in progress prior to start doing brick work. |
|
|
Aprial 2006
|
The topping concrete and plastering work at corridor area have been completed. |
|
|
Aprial 2006
|
The installation of new water tank at 2nd sty is completely done. |
|
|
Aprial 2006
|
Laying of block work for Transformer room at Basement-1 is in progress. |
|
|
Aprial 2006
|
The initial setting up of hydraulic pumps and jack are being repared for 3rd jacking up |
|
|
Aprial 2006
|
Brick laying , plastering work & 1st fix of M&E Services for all units at 8th sty are being carried out |
|
|
Aprial 2006
|
Most of the units at 9th sty for laying of brick and block are in progress as well as topping concrete work prior to start tiling work. |
|
|
Aprial 2006
|
Overall Work Progress at View ( A ) |
|
|
Aprial 2006
|
Overall Work Progress at View ( B ) |
|
|
Aprial 2006
|
Overall Work Progress at View ( C ) |
|
|
Aprial 2006
|
Overall Work Progress at View ( D ) |
|
|
May 2006
|
16th floor sector A concreting was finished and sector B slab formwork is in progress. |
|
|
May 2006
|
Swimming Pool construction is in progress |
|
|
May 2006
|
Refuse Chute Construction is in progress |
|
|
May 2006
|
Transformer Room construction works at the Basement - Block works is in progress and demolishing of existing structures is 95% completed. |
|
|
May 2006
|
A Sand pump is brought to the site and it is in operation to pump sand to upper floors |
|
|
May 2006
|
Podium area construction is in progress |
|
|
May 2006
|
S1 Stair case construction from 3rd to 5th floor is in progress. |
|