Date
Description
View
     
March 2006
Overall Work Progress at View ( C )
March 2006
Overall Work Progress at View ( D )
Aprial 2006
14th sty slab has been cast at (Sector-A) and curing is being carried out for (7-days).
Aprial 2006
Some of columns from 14th to 15th sty have been cast and the offset level to the floor is being marked for reference during construction activities.
Aprial 2006
The cleanliness is completely done and the survey setting out for Architectural Work is in progress prior to start doing brick work.
Aprial 2006
The topping concrete and plastering work at corridor area have been completed.
Aprial 2006
The installation of new water tank at 2nd sty is completely done.
Aprial 2006
Laying of block work for Transformer room at Basement-1 is in progress.
Aprial 2006
The initial setting up of hydraulic pumps and jack are being repared for 3rd jacking up
Aprial 2006
Brick laying , plastering work & 1st fix of M&E Services for all units at 8th sty are being carried out
Aprial 2006
Most of the units at 9th sty for laying of brick and block are in progress as well as topping concrete work prior to start tiling work.
Aprial 2006
Overall Work Progress at View ( A )
Aprial 2006
Overall Work Progress at View ( B )
Aprial 2006
Overall Work Progress at View ( C )
Aprial 2006
Overall Work Progress at View ( D )
May 2006
16th floor sector A concreting was finished and sector B slab formwork is in progress.
May 2006
Swimming Pool construction is in progress
May 2006
Refuse Chute Construction is in progress
May 2006
Transformer Room construction works at the Basement - Block works is in progress and demolishing of existing structures is 95% completed.
May 2006
A Sand pump is brought to the site and it is in operation to pump sand to upper floors
May 2006
Podium area construction is in progress
May 2006
S1 Stair case construction from 3rd to 5th floor is in progress.