Date |
Description |
View |
| |
|
|
|
May 2006
|
Brick laying , plastering work & 1st fix of M&E Services for all units up to 11th sty are being carried out |
|
|
May 2006
|
Most of the units at 10th sty for laying of brick and block are in progress. |
|
|
May 2006
|
S1 Stair case casting was completed up to 14th Floor and 14th to 15th is in progress |
|
|
May 2006
|
Up to 13th Floor cleaning finished and ready for Architectural works |
|
|
June 2006
|
Laying of rebar ( bottom & top ) is being done prior to casting at Sector”B” of 17th Sty. |
|
|
June 2006
|
The dismantling, flying and setting of table forms are carried out at 18th sty by LF Construction. |
|
|
June 2006
|
Most of R.C columns/ shear walls have been completed with good quality of concrete from 18th to 19th sty |
|
|
June 2006
|
The dismantling of formworks and cleanliness have been completed prior to start Architectural Works at 16th sty. |
|
|
June 2006
|
The good quality of concrete surface at stair case core wall using Doka Climbing System Formwork at 21st Sty is seen. |
|
|
June 2006
|
The installation of Aluminum work at 8th sty is in progress |
|
|
June 2006
|
The water pending test is in progress after waterproofing work is done to ensure there is no water leakage at all at Corridor area |
|
|
June 2006
|
The installation of M&E Service duct & timber door frames at central corridor are in progress |
|
|
June 2006
|
The tiling works of kitchen area at 7th storey is being done |
|
|
June 2006
|
The installation of Pre-cast Refuse Chute is progressively done and which is now at 5th sty Slab |
|
|
June 2006
|
The licensed Surveyor is doing leveling check on settlement markers as monthly basis to ensure that readings taken are within the tolerance during construction stage and currently, progress of work is at 18th sty level |
|
|
June 2006
|
Overall work progress at View ( A ) |
|
|
June 2006
|
Overall work progress at View ( B ) |
|
|
June 2006
|
Overall work progress at View ( C ) |
|
|
June 2006
|
Overall work progress at View ( D ) |
|
|
July 2006
|
The formwork and bottom mesh have been completed and the laying of conduit pipe is being done prior to laying of top reinforcement mesh at 21st Sty |
|
|
July 2006
|
Some of the column cast with good quality of concrete are completed in partial at 21 sty of Sector ( B ) |
|
|
July 2006
|
The dismantling of beam & slab table forms are completely done and the cleanliness is being done prior to start Architectural Work at 15th Sty. |
|