Date
Description
View
     
May 2006
Brick laying , plastering work & 1st fix of M&E Services for all units up to 11th sty are being carried out
May 2006
Most of the units at 10th sty for laying of brick and block are in progress.
May 2006
S1 Stair case casting was completed up to 14th Floor and 14th to 15th is in progress
May 2006
Up to 13th Floor cleaning finished and ready for Architectural works
June 2006
Laying of rebar ( bottom & top ) is being done prior to casting at Sector”B” of 17th Sty.
June 2006
The dismantling, flying and setting of table forms are carried out at 18th sty by LF Construction.
June 2006
Most of R.C columns/ shear walls have been completed with good quality of concrete from 18th to 19th sty
June 2006
The dismantling of formworks and cleanliness have been completed prior to start Architectural Works at 16th sty.
June 2006
The good quality of concrete surface at stair case core wall using Doka Climbing System Formwork at 21st Sty is seen.
June 2006
The installation of Aluminum work at 8th sty is in progress
June 2006
The water pending test is in progress after waterproofing work is done to ensure there is no water leakage at all at Corridor area
June 2006
The installation of M&E Service duct & timber door frames at central corridor are in progress
June 2006
The tiling works of kitchen area at 7th storey is being done
June 2006
The installation of Pre-cast Refuse Chute is progressively done and which is now at 5th sty Slab
June 2006
The licensed Surveyor is doing leveling check on settlement markers as monthly basis to ensure that readings taken are within the tolerance during construction stage and currently, progress of work is at 18th sty level
June 2006
Overall work progress at View ( A )
June 2006
Overall work progress at View ( B )
June 2006
Overall work progress at View ( C )
June 2006
Overall work progress at View ( D )
July 2006
The formwork and bottom mesh have been completed and the laying of conduit pipe is being done prior to laying of top reinforcement mesh at 21st Sty
July 2006
Some of the column cast with good quality of concrete are completed in partial at 21 sty of Sector ( B )
July 2006
The dismantling of beam & slab table forms are completely done and the cleanliness is being done prior to start Architectural Work at 15th Sty.