Date
Description
View
     
July 2006
The laying of cement block work adjacent to the central corridor is in progress.
July 2006
The installation of bricks at type A-3 Unit next to Stair-case (1) is being done prior to do installation of Aluminium frame.
July 2006
The installation of aluminium frame at A-2 Unit (10th sty) has been completely done and for those at other units of 10th sty onward are being installed.
July 2006
The plastering work, screeding have been done and the installation of ceiling grid, tiling work and M&E Services are being carried out.
July 2006
The floor screeding work is in progress at 11th sty
July 2006
The cement block laying at 16th sty is in progress.
July 2006
Overall work progress at View ( A )
July 2006
Overall work progress at View ( B )
July 2006
Overall work progress at View ( C )
July 2006
Overall work progress at View ( D )
August 2006
The Jacking Up of Tower Crane which can serve up to 28th sty height is completed
August 2006
The 23rd sty slab cast is completed and erection of column rebar in progress.
August 2006
The erection of formwork at Swimming Pool area ( Lower deck + Upper deck ) have been completed.
August 2006
The skim coat at stair-case ( 1 ) is being done at 7th sty.
August 2006
Overall work progress at View ( A )
August 2006
Overall work progress at View ( B )
August 2006
Overall work progress at View ( C )
August 2006
Overall work progress at View ( D )
September 2006
After casting the 25th Floor Sector A – Formwork of columns & walls are in progress
September 2006
Erection of Formwork for 25th Floor Sector B is in progress
September 2006
Preparation works are in progress for 27th sty stair case wall casting
September 2006
Rebar work has been resume at swimming pool and the site engineer is checking the stirrups of a beam
September 2006
The cement block laying at 21st sty is in progress.
September 2006
The floor screeding work is in progress at 14th sty.