Date |
Description |
View |
| |
|
|
|
July 2006
|
The laying of cement block work adjacent to the central corridor is in progress. |
|
|
July 2006
|
The installation of bricks at type A-3 Unit next to Stair-case (1) is being done prior to do installation of Aluminium frame. |
|
|
July 2006
|
The installation of aluminium frame at A-2 Unit (10th sty) has been completely done and for those at other units of 10th sty onward are being installed. |
|
|
July 2006
|
The plastering work, screeding have been done and the installation of ceiling grid, tiling work and M&E Services are being carried out. |
|
|
July 2006
|
The floor screeding work is in progress at 11th sty |
|
|
July 2006
|
The cement block laying at 16th sty is in progress. |
|
|
July 2006
|
Overall work progress at View ( A ) |
|
|
July 2006
|
Overall work progress at View ( B ) |
|
|
July 2006
|
Overall work progress at View ( C ) |
|
|
July 2006
|
Overall work progress at View ( D ) |
|
|
August 2006
|
The Jacking Up of Tower Crane which can serve up to 28th sty height is completed |
|
|
August 2006
|
The 23rd sty slab cast is completed and erection of column rebar in progress. |
|
|
August 2006
|
The erection of formwork at Swimming Pool area ( Lower deck + Upper deck ) have been completed. |
|
|
August 2006
|
The skim coat at stair-case ( 1 ) is being done at 7th sty. |
|
|
August 2006
|
Overall work progress at View ( A ) |
|
|
August 2006
|
Overall work progress at View ( B ) |
|
|
August 2006
|
Overall work progress at View ( C ) |
|
|
August 2006
|
Overall work progress at View ( D ) |
|
|
September 2006
|
After casting the 25th Floor Sector A – Formwork of columns & walls are in progress |
|
|
September 2006
|
Erection of Formwork for 25th Floor Sector B is in progress |
|
|
September 2006
|
Preparation works are in progress for 27th sty stair case wall casting |
|
|
September 2006
|
Rebar work has been resume at swimming pool and the site engineer is checking the stirrups of a beam |
|
|
September 2006
|
The cement block laying at 21st sty is in progress. |
|
|
September 2006
|
The floor screeding work is in progress at 14th sty. |
|